To comprehensively improve agricultural production base and enhance agricultural productivity through regionalization of rivers, reorganization of land, improvement of drainage and reclamation
Applicable Laws
Agricultural and Fishing Villages Improvement Act, and Public Waters Management and Reclamation Act
Funding
Farmland management fund (100% national budget)
Project Entity
Korea Rural Community Corporation (KRCC)
Project Procedures
Set basic plan (MAFRA) ⇒ Designate the business entity (MAFRA) ⇒ Set an enforcement plan (KRCC) ⇒ Approve and notify the enforcement plan (MAFRA) ⇒ Execute the project (KRCC) ⇒ Construct (MAFRA)
Development Type
Land Type: To develop industrial water, improve drainage, and organize existing farmland
Land Type and Coastal area: To simultaneously develop existing farmland and reclaim farmland
Since 1998, new reclamation projects have been suspended according to governmental policy
Category
District Titles
Development Type
Financial Source
Land Type (5)
Geumgang II, Hongbo, Yeongsangang IV, Seosan A, Convenient farming in Geumgang district
Existing farmland development - Industrial water development, drainage improvement, farmland organization, etc. * Repairing old facilities: Seosan A
Reclaimed farmland and existing farmland development - Reclaimed farmland and industrial water development, etc. * Reclaimed Farmland Development: Sihwa, Haong * Reclaimed and Land Development: Yeongsangang III-1, Yeongsangang III-2
Progress by District
사업지구에따른 사업기간, 총사업비, 사업규모를 설명하는 표
Category
Description
Project Period
Geumgang II District
1989 ~ 2022
Hongbo District
1991 ~ 2025
Yeongsangang IV District
2001 ~ 2027
Seosan A Rearrangement
2008 ~ 2024
Yeongsangang III-1 District
1995 ~ 2023
Yeongsangang III-2 District
1997 ~ 2022
Hwaong District
1991 ~ 2022
Sihwa District
1998 ~ 2024
Convenient farming in Geumgang district
2021 ~ 2031
Total Project Cost
Geumgang II District
KRW 957.3 billion (Until 2020: KRW 907.7 billion)
Hongbo District
KRW 608.4 billion (Until 2020: KRW 493.8 billion)
Yeongsangang IV District
KRW 938.1 billion (Until 2020: KRW 528.8 billion)
Seosan A Rearrangement
KRW 300.5 billion (Until 2020: KRW 227.3 billion)
Yeongsangang III-1 District
KRW 602.9 billion (Until 2020: KRW 518.7 billion)
Yeongsangang III-2 District
KRW 419.0 billion (Until 2020: KRW 412.9 billion)
Hwaong District
KRW 983.3 billion (Until 2020: KRW 788.8 billion)
Sihwa District
KRW 437.1 billion (Until 2020: KRW 223.7 billion)
Convenient farming in Geumgang district
KRW 414.6 billion (Basic survey in 2021)
Project Size
Geumgang II District
13 pumping stations, 610㎞ of waterway, and 16,251 ha of land readjustment
Hongbo District
2.9㎞ of breakwater, 6 pumping stations, 408㎞ of waterway
Yeongsangang IV District
10 pumping stations, 7 control reservoirs and 487㎞ of waterway
Seosan A Rearrangement
34.9㎞ of breakwater, 5 pumping and drainage stations, and 499㎞ of waterways and drainage
Yeongsangang III-1 District
7,960 ha of internal reclamation, 2 pumping stations, and 171.1㎞ of waterway
Yeongsangang III-2 District
4,540 ha of internal reclamation, 2 pumping stations, and 85.9㎞ of waterway
Hwaong District
9.8㎞ of breakwater, 37㎞ of flood control bank, 2 pumping stations, and 4,482 ha of internal reclamation
Sihwa District
37.6㎞ of breakwater, 3 pumping stations, 15.9㎞ of raceway and 3,636 ha of internal reclamation
Convenient farming in Geumgang district
6,515ha of land readjustment, 1,397ha of land reorganization and 142km of waterway